Reschedule Release/Cycle/Milestone Dialog Box
This dialog box enables you to reschedule the start and end date of a release, cycle, or milestone.
| To access
|
In the Releases module, right-click a release, cycle, or milestone. Select Reschedule.
|
| Important information
|
-
When rescheduling a release, the related cycles, milestones, and KPI thresholds are rescheduled accordingly.
-
When rescheduling a milestone, the related KPI thresholds are rescheduled accordingly.
|
| Relevant tasks
|
|
| See also
|
|
User interface elements are described below:
|
UI Element
|
Description
|
| Start Date
|
The date on which the release, cycle, or milestone starts.
|
| End Date
|
The date on which the release or cycle ends.
Available from: Reschedule Release/Cycle dialog box
|
| Due Date
|
The date on which the milestone ends.
Available from: Reschedule Milestone dialog box
|