Reschedule Release/Cycle/Milestone Dialog Box
This dialog box enables you to reschedule the start and end date of a release, cycle, or milestone.
To access
|
In the Releases module, right-click a release, cycle, or milestone. Select Reschedule.
|
Important information
|
-
When rescheduling a release, the related cycles, milestones, and KPI thresholds are rescheduled accordingly.
-
When rescheduling a milestone, the related KPI thresholds are rescheduled accordingly.
|
Relevant tasks
|
|
See also
|
|
User interface elements are described below:
UI Element
|
Description
|
Start Date
|
The date on which the release, cycle, or milestone starts.
|
End Date
|
The date on which the release or cycle ends.
Available from: Reschedule Release/Cycle dialog box
|
Due Date
|
The date on which the milestone ends.